MINISTRY OF WATER AND NATURAL RESOURCES.

Environment, Water and Natural Resources
The department is responsible for the conservation, control and protection of the environment and natural resources. It is also responsible for coordinating the implementation and enforcement of environmental regulations and standards.

It implements specific national government policies on natural resources and environmental conservation, including soil and water conservation, forestry, public nuisance and pollution. The overall responsibility of the department is to ensure that county residents enjoy a clean and healthy environment.

WATER PROJECTS IMPLEMENTATION STATUS JULY 2015

JULY 2015

Project Name Constituency/

Ward

Activities/ Outputs Key Performance Indicator Budget (Ksh) Status
Kerita Tee Cherangany/Sinyereri/Makutano Connection of Tee and Pipeline Extension ·   6 Km of pipeline extended

·   1 storage facility constructed

·   8,000 people to access piped water 4,018,000 Procurement
Chepkoiyo Tee

 

·   Cherangany/ Sitatunga Connection of Tee and Pipeline Extension ·   5 Km of pipeline extended

·   1 No. 50m3 storage facility constructed

·   4,000 people to access piped water 3,493,925  

95% Completed

Wamuini B ·   Kiminini/ Waitaluk Connection of Tee and Pipeline Extension

 

·   3 Km of pipeline extended

·   1 No. 50m3 storage facility constructed

·   Construction of 1No. Water Kiosk

·   2500 people to access piped water 2,494,650 Ongoing
Kapsara SDA ·   Cherangany/Makutano/

Sinyereri

Connection of Tee and Pipeline Extension

 

·   3 Km of pipeline extended

·   1 No. 50m3 storage facility constructed

·   Construction of 1No. Water Kiosk

·   2000 people to access piped water 1,500,500 Completed
Amagoro- Kimoson ·   Kiminini/ Waitaluk Connection of Tee and Pipeline Extension

 

·   6 Km of pipeline extended

·   1 No. 50m3 storage facility constructed

·   Construction of 1No. Water Kiosk

·   3,000 people to access piped water 4,828,700  

95% Completed

Matisi ·   Saboti/ Matisi Connection of Tee and Pipeline Extension

 

·   3 Km of pipeline extended

·   1 No. 50m3 storage facility constructed

·   Construction of 1No. Water Kiosk

·   2,500 people to access piped water 2,859,050  

90% Completed

Machewa ·   Saboti/ Machewa Water gravity scheme ·   2 Km of pipeline extended

·   Construction of 1No. Water Kiosk

·   1,500 people to access piped water 1,500,000 Procurement
Suam – Orchard ·   Endebess/

Chepchoina

Water Gravity Schemes ·   6 Km of pipeline extended

·   Construction of 1No. Water Kiosk

·   2,000 people to access piped water 4,898,988 Completed
Suwerwa ·   Cherangany/ Suwerwa Water Gravity Schemes ·   Construction of Intake

·   2Km Pipeline extension

·   1,500 people to access piped water 2,808,200 Completed
Masaba ·   Endebess/ Matumbei Water Gravity Schemes

 

 

 

·   14 Km of pipeline extended

·   1 No. 100m3 storage facility constructed

·   Construction of 4No. Water Kiosk

·   Construct 10m3 BPT

·   5,000 people to access piped water 9,424,355 Completed
Kiboroa ·   Saboti/ Saboti Water Gravity Schemes

 

·   9 Km of pipeline extended

·   Construction of 2No. Water Kiosk

·   5,000 people to access piped water 2,869,445 90% Completed
Chepinyiny ·   Cherangany/ Chepsiro Water Gravity Schemes

 

·   3 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   2,500 people to access piped water 4,458,000 Completed
Kimwondo ·   Endebess / Matumbei Water Gravity Schemes

 

 

·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   Pipe fittings to water tank

·   2,000 people to access piped water 5,141,330 Procurement
Kiptogot- Kolongolo ·   Endebess / Chepchoina- Kwanza Water Gravity Schemes

 

·   Conduct a feasibility and design of the proposed Kiptogot – Kolongolo water supply project ·   Detailed design of the project and anticipated cost 1,500,000 Design Completed
Suwerwa ·   Cherangany / Suwerwa Water Gravity Schemes

 

 

 

·   6 Km of pipeline extended

·   Protection of 3No. Spring sources

·   Construction of 1No. Water Kiosk

·   15,000 people to access safe water 1,029,950 Procurement
Mosongo -Tenden ·   Cherangany / Kiptoror/Chepsiro Water Gravity Schemes

 

 

 

·   Conduct a Reconnaissance on the proposed water project that covers parts of Trans Nzoia, Marakwet and Uasin Gishu counties ·   Pre- Feasibility Study done Pre- Feasibility Study yet to be done
Mt. Elgon Kisawai ·   Endebess/ Saboti Water Gravity Schemes ·   Extension of pipeline from Mt. Elgon water project to Kisawai ·   25,000 people to access piped water 14,721,200 Procurement
Sosio – Teldet ·   Saboti / Kiminini Water Gravity Schemes

 

 

·   Conduct a feasibility and design of the proposed Sosio – Teldet water supply project ·   Detailed design of the project and anticipated cost 1,195,000 Design Complete
Bondeni – Chalicha ·   Saboti/ Machewa Water Gravity Schemes

 

·   6 Km of pipeline extended

·   1 No. 100m3 storage facility constructed

·   7,000 people to access piped water 2,422,050 Procurement
Yuya- Kaplamai ·   Cherangany / Motosiet Water Gravity Schemes

 

 

·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   Pipe fittings to water tank

·   2,000 people to access piped water 1,980,630 Procurement
Sitatunga- W/P ·   Cherangany / Sitatunga Water Gravity Schemes

 

 

·   Construction of 4No. water points

·   2 Km of pipeline extended

·   Construction of 1No. Water Kiosk

·   4,000 people to access safe and piped water 2,491,800 Procurement
Arba- Kesogon ·   Cherangany / Sinyereri Water Gravity Schemes

 

·   2 Km of pipeline extended to Wiyeta

·   Construction of 1No. Water Kiosk

·   Rehabilitation of Masonry Tank

·   2,000 people to access piped water 1,498,200 Procurement
Sibanga – Surungai ·   Cherangany / Motosiet Connection and Pipeline Extension ·   6 Km of pipeline extended

·   Pipe fittings to water tank

·   2,000 people to access piped water 2,973,596 Procurement
Makutano – Bwake ·   Cherangany / Makutano Connection and Pipeline Extension ·   2 Km of pipeline extended

·   Pipe fittings to water tank

·   2,000 people to access piped water 1,510,775 Procurement
Chepkaitit – Kiptenten ·   Cherangany / Suwerwa Connection and Pipeline Extension ·   6 Km of pipeline extended

·   Procurement of pipes and fittings

 

·   1,000 people to access piped water 11,766,620 Procurement
Liyavo – Kapsitwet ·   Kiminini/ Sirende Connection and Pipeline Extension

 

·   5 Km of pipeline extended

·   Construction of Valve chamber

·   Construction of Tank Tower and Installation of Tank

·   Pipe fittings to water tank

·   3,000 people to access piped water

·   Milk cooling plant to be connected

3,000,000 85% Completed
Kibomet – Legacy ·   Kiminini/ Hospital Connection and Pipeline Extension ·   2 Km of pipeline extended

·   Pipe fittings to water tank

·   2,000 people to access piped water 1,539,774 Procurement
Kapkoi – Mabonde ·   Kiminini/ Waitaluk Connection and Pipeline Extension

 

·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   Pipe fittings to water tank

·   2,000 people to access piped water 1,000,000 Procurement
Serena/Kapretwo ·   Saboti/ Saboti Water gravity scheme ·   2 Km of pipeline extended

·   Construction of 1No. Water Kiosk

·   1,500 people to access piped water 1,499,820 Procurement
Toro -Extension ·   Kiminini/ Sirende Connection and Pipeline Extension ·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   2,000 people to access piped water 1,000,000 Procurement
Toro B- Kaptieng ·   Kiminini/ Sirende Connection and Pipeline Extension ·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   2,000 people to access piped water 1,500,000 Procurement
Matisi ·   Saboti/ Matisi Connection and Pipeline Extension ·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

·   3,000 people to access piped water 1,635,448 Procurement
Tuwani ·   Saboti / Matisi Connection of Tee and Pipeline Extension

 

·   2 Km of pipeline extended

·   Construction of water Kiosk

·   Construction of water point

 

·   3,000 people to access piped water 1,500,000 Procurement
Bidii ·   Kwanza/ Bidii Connection of Tee and Pipeline Extension ·   2 Km of pipeline extended

·   Construction of 1No. Valve chamber

 

·   2,000 people to access piped water 1,450,000 Procurement
Kiungani – Birunda ·   Kiminini/ Nabiswa Connection of Tee and Pipeline Extension ·   Pipeline extended

·   Construction of 1No. Valve chamber

·   2,000 people to access piped water 2,549,951 Procurement
Kwanza Kwanza/ Kwanza Borehole at Amuka ·   Drilling and equipping Borehole with storage ·   3,000 people to access piped water 3,000,000
Keiyo Kwanza/ Keiyo Construction and protection of water points ·   Construction of water points

 

·   4,000 people to access safe water 1,406,640 Procurement
Drilling of Boreholes County Wide Drilling of Boreholes ·   Purchase drilling Equipment ·   Drilling and equipping of Boreholes and people to access safe water        33,500,000 Supplied
Purchase Solar Pump accessories

/Tanks /

platform

·   Procurement of solar pumping facilities ·   3No. 6,600,000 Procurement
Spring Protection

 

County Wide ·   Catchment Protection and

Construction of 20 No. Spring protection and auxiliary works

·   No of Spring protection constructed

·   No of catchments protected

·   5,000 No. people benefiting from the improved water source 4,073,999 Procurement
Rehabilitation of dam

 

County Wide ·   Rehabilitate 1No. Water dam -Weonia ·   Increased storage and control floods

 

·    1 No. Dams rehabilitated 4,232,900 Procurement
Machinjoni sewerage rehabilitation Saboti/Tuwan ·   Rehabilitation of sewerage treatment plant intake

·   Rehabilitation of primary and secondary sedimentation tank including all valves

·   Drying beds/sludge thickener repair.

·   Rehabilitation of trickling filters

·   Installation of recycling pumps

·   Cleaned environment ·    15,000 persons to be served  

8,500,000

 

Procurement